Complete renovation of the Beverentunnel

Algemeen Overzicht

Datum

Status

Binnenkort

Provincie

Plaats

Weg

R2

Why a renovation?

The Beverentunnel is in need of modernisation. This is why we are planning a complete renovation. We will be making alterations to the structure and supply systems, while getting the tunnel ready to meet the energy- and climate-related challenges of the future.

  • We will conduct inspections in the spring of 2024 in preparation for renovation.
  • From 12 April 2024 we will conduct preliminary work on the diversion route. 
  • The renovation will start on 8 July 2024. The construction works will last for six months in each direction. The Beverentunnel will be closed to traffic heading towards Ghent for one year and a diversion will be in effect. You will still be able to drive through the tunnel in the direction of the Netherlands. 
  • If  all runs smoothly, the renovated tunnel will open in late summer 2025
  • We will conduct some more safety tests as of August 2025.

Overview of the project timeline. Click on the image to enlarge.